UK defence prime Babcock has begun a dispute resolution process (DRP) with the UK Ministry of Defence (MoD) to determine liability for increased costs being sustained on the Type 31 frigate programme, with up to £100m in additional funds needed.   

Providing a 2023 financial year and Type 31 programme update on 20 April, Babcock said it recognised over £600m in revenue on the Type 31 programme, which remained on schedule and due to conclude in 2028. However, the programme’s production plan was described as “demanding”, given the impact felt by UK industry during the Covid-19 pandemic, and had seen an increase in actual and projected costs.

Continuing, Babcock said that despite having been in dialogue with the MoD as to who is responsible for the additional costs under the contract, it had been “unable to reach agreement” and as such, has seen a DRP commence. A DRP could result in arbitration to determine who should bear the increased costs of the programme.

“If the contractual position remains unresolved, the lack of recovery of these additional costs would need to be reflected in the Group’s FY23 year end results. Without recovery of the additional costs, the contract would be loss-making and our preliminary assessment, subject to finalisation and audit, is that a one-off provision of between £50 million and £100 million would be required to cover the duration of the contract,” read the Babcock statement.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The original contact was signed in November 2019 to deliver five Inspiration-class Type 31 general purpose frigates, at an average production cost of £250m per vessel. The first-in-class of the Type 31s, HMS Venturer, is due to be structurally complete in December 2023 and construction commenced on the second ship, HMS Active, in January 2023.

Speaking to Naval Technology on the potential for delays to the Type 31 as a result of the DRP, an MoD spokesperson said “as Babcock has made clear” the programme “remains on schedule”.

The spokesperson added that the MoD would not comment on contract discussions.

Crucial programme for shrinking fleet

The Type 31 build is intended to quickly deliver five general purpose frigates into Royal Navy service to replace five outgoing, and ageing, Type 23 vessels. Any delays in the Type 31 build, which already looks tight given the turnaround of effectively one vessel per year, will impact a Royal Navy surface combatant force that looks set to dip to 15 hulls by the middle of the decade.

According to the UK’s shipbuilding programme, five Type 31 Inspiration-class general-purpose frigates will be introduced into Royal Navy service from 2027, with Babock completing the handover of the fifth and final vessel the following year.

Following each handover, the Royal Navy will begin a test and trials programme to ensure the vessel is ready for service, with HMS Venturer’s own programme due to be around four years long.

The Type 31 class was born from the realisation by the UK MoD that it could not afford to acquire 13 Type 26 anti-submarine warfare frigates from UK defence prime BAE Systems, instead constraining that programme to eight hulls. A stop-start competition to determine an alternative five-ship frigate requirement was won by Babcock using its Arrowhead 140 design, heavily derived from the Danish Iver Huitfeldt-class frigates.