The US Navy’s second Gerald R Ford-class aircraft carrier USS John F Kennedy (CVN 79) has reached 50% completion in its construction.

The construction milestone was reached by Huntington Ingalls Industries (HII) Newport News Shipbuilding division with the installation of one of the largest units on board.

Discover B2B Marketing That Performs

Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.

Find out more

Known as a superlift, the approximately 905 metric tonne ship unit is one of the heaviest of the planned steel structures.

The aft section was placed between the hangar bay and flight deck of the nuclear-powered US Navy ship.

The superlift comprises 19 smaller units. It enabled Newport News Shipbuilding to install a majority of the outfitting equipment such as grating, pumps, valves, electrical panels, mounting studs, and ventilation before the structure was hoisted into the dry dock using the shipyard’s 1,050 metric tonne gantry crane.

“The aircraft carrier is due to be moved from the dry dock to an outfitting berth in the fourth quarter of next year, approximately three months ahead of schedule.”

The superlifts will be joined together to complete the construction of the Gerald R Ford-class aircraft carrier.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

CVN 79 programme director Mike Butler said: “This superlift represents the future build strategy for Ford-class carriers.

“Not only did we build this superlift larger and with significantly more pre-outfitting, we managed much of the work on the deckplate with new digital project management tools as part of our integrated digital shipbuilding initiative.”

The aircraft carrier is due to be moved from the dry dock to an outfitting berth in the fourth quarter of next year, approximately three months ahead of schedule.

The USS John F Kennedy will have a full load displacement of approximately 100,000 long tonnes and will be able to sail at a speed of more than 30k.

On 5 June 2015, HII secured a $3.35bn contract for the detail design and construction of the aircraft carrier, while the keel on the ship was laid on 22 August 2015.

Naval Technology Excellence Awards - Nominations Closed

Nominations are now closed for the Naval Technology Excellence Awards. A big thanks to all the organisations that entered – your response has been outstanding, showcasing exceptional innovation, leadership, and impact.

Excellence in Action
Virtualitics has secured the Innovation and Business Expansion awards for its Integrated Readiness Optimization (IRO) suite. Discover how its explainable AI is transforming maintenance, sustainment and mission readiness, giving defence leaders faster, clearer, and more confident operational decisions.

Discover the Impact