The US Navy and General Dynamics (GD)-Bath Iron Works (BIW) have reached an agreement to build the second and third DDG 1000 Zumwalt-class destroyers, navy acquisition official Sean Stackley said.
Defence News has quoted the official as saying: “The navy has reached an agreement with General Dynamics-Bath Iron Works for pricing, terms and conditions for DDGs 1001 and 1002.”
The agreement was needed to ensure a fixed price contract in line with the Navy’s ‘should cost’ estimates and the continuation of shipbuilding work at BIW shipyard.
The construction of the Zumwalt destroyer has been under way since February 2009 and a keel-laying ceremony is scheduled to be held in November this year.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataWork on the second ship has been initiated with long-lead construction items, but a definitive construction contract is required to proceed to next levels.
See Also:
The contract agreements were delayed due to a Nunn-McCurdy review, which revised the Navy’s decision to build three, rather than seven units of the class, thereby increasing unit costs.